Utilities Master Plan Summary

 
 
The OSU Board of Regents approved the start of a Utilities Master Plan (UMP) in March of 2014 to accomplish the following deliverables:
  • Thermodynamic Steam Model
  • Hydraulic Chilled Water Model
  • Dynamic Electrical Model
  • Utility Geographic Information System (GIS)
  • Plan for Correcting Existing Deficiencies
  • 5-Year Plans for Steam, Chilled Water, and Electrical
  • 20-Year Plans for Steam, Chilled Water, and Electrical
  • New Central Plant Location & Size Recommendations 

The UMP was completed as of June 30, 2016.